Current Status :
HIG - Aria
MIG - Terra
LIG - Acqua
Current Status as on 17-12-2008
< Previous
Auto/Stop
Next >
HIG-Tower 2
4th Floor slab casting in progress, 50% completed.
HIG-Tower 3
Shuttering & reinforcement work for 2nd Floor Slab in Progress.
HIG-Tower 6
Foundation work started.
HIG-Tower 4
Shuttering & reinforcement work for 3rd Floor Slab in Progress.
MIG I - Terra
Work has just started.
MIG II - Terra
Work has just started.
LIG - Acqua
Work has just started.
HIG-Tower 1
Shuttering & reinforcement work for 1st Floor Slab in Progress.